Program Management Professional (PgMP) — Question 253
A company wants to perform a preliminary stakeholder analysis to assess a new program's support.
What should the program manager develop?
Answer options
- A. Program communications management plan and the stakeholder charter
- B. Responsible, accountable, consult, and inform (RACI) matrix, stakeholder list, and escalation process
- C. Stakeholder strengths, weaknesses, opportunities and threats (SWOT) analysis
- D. Stakeholder engagement plan, stakeholder register, and stakeholder map
Correct answer: D
Explanation
The correct answer, D, includes essential tools such as the stakeholder engagement plan, stakeholder register, and stakeholder map, which are crucial for identifying and managing stakeholder relationships effectively. Options A, B, and C do not encompass the full breadth of stakeholder analysis and engagement required for a new program's support assessment.