Program Management Professional (PgMP) — Question 253

A company wants to perform a preliminary stakeholder analysis to assess a new program's support.
What should the program manager develop?

Answer options

Correct answer: D

Explanation

The correct answer, D, includes essential tools such as the stakeholder engagement plan, stakeholder register, and stakeholder map, which are crucial for identifying and managing stakeholder relationships effectively. Options A, B, and C do not encompass the full breadth of stakeholder analysis and engagement required for a new program's support assessment.