Program Management Professional (PgMP) — Question 250

Performing quality assurance in a program can result in which one of the following?

Answer options

Correct answer: D

Explanation

Conducting quality assurance often leads to the identification of issues that may require modifications in the project, which results in change requests (D). The other options, while related to quality and project management, do not directly arise specifically from the quality assurance process.