Program Management Professional (PgMP) — Question 249

You are the program manager for your organization. When a project in your program is completed, who will need to sign the certificate of completion?

Answer options

Correct answer: B

Explanation

The correct answer is B, the program customer, because they are the ones who have a vested interest in the project's outcomes and are typically responsible for formally accepting the completed work. The project manager (A) manages the project but does not sign the completion certificate; program stakeholders (C) may provide input but do not have the authority to sign, and the project management team (D) oversees the project but does not hold signing authority for completion.