Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?

Answer options

Correct answer: D

Explanation

Holly is working on the Interface management plan because it specifically addresses the interactions needed with various stakeholders to ensure the program's progress. The Stakeholder management plan focuses more on identifying and analyzing stakeholders rather than detailing interactions. The Communications management plan emphasizes the methods of communication, while the Human resource management plan deals with team management and resources, not direct stakeholder interactions.