Program Management Professional (PgMP) — Question 203
A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?
Answer options
- A. Program risk
- B. Program benefits
- C. Program scope
- D. Link to organizational strategy
Correct answer: C
Explanation
The correct answer is C, Program scope, as defining the scope typically occurs after the initiation phase when more detailed planning is involved. In contrast, program risk, program benefits, and the link to organizational strategy are identified during the initiation phase to ensure alignment with the organization's goals.