Program Management Professional (PgMP) — Question 195

After new private equity owners acquire an enterprise, they want to improve its value by reducing costs. A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed. A strategic component project presents significant risk to organizational objectives due to its complexity and dependencies on external parties. After a series of board meetings, the enterprise's investment committee approves a budget to implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility. Implementation of this component project may now begin, but is already one month behind schedule. The program manager now perceives significantly more risk to the larger program due to this delay.
What should the program manager do to address this risk with the program sponsor and governance board?

Answer options

Correct answer: B

Explanation

The correct answer is B because it involves updating all relevant documentation and directly collaborating with the program sponsor to address the changes necessitated by the delay. This approach ensures all risks are properly documented and communicated, which is essential for informed decision-making. The other options either focus on unilateral actions or insufficiently address the need for collaboration with the program sponsor and governance board.