Program Management Professional (PgMP) — Question 169
An R&D group director approves a major program's charter. Although the director has a high level of understanding of the program's scope, they are unsure of how the program manager can be successful in delivering the program's commitments.
What should the program manager do to align stakeholders with planning and monitoring the program's progress?
Answer options
- A. Establish high-level program milestones
- B. Develop an accountability matrix, and assign program roles and responsibilities
- C. Generate a supplier management plan to identify external stakeholders
- D. Create a communications management plan, and establish reporting formats
Correct answer: A
Explanation
Establishing high-level program milestones is essential for aligning stakeholders as it provides clear targets and timelines for the program's progress. The other options are important as well, but they focus on specific roles, external stakeholders, or communication strategies rather than the overarching alignment through milestones.