Program Management Professional (PgMP) — Question 169

An R&D group director approves a major program's charter. Although the director has a high level of understanding of the program's scope, they are unsure of how the program manager can be successful in delivering the program's commitments.
What should the program manager do to align stakeholders with planning and monitoring the program's progress?

Answer options

Correct answer: A

Explanation

Establishing high-level program milestones is essential for aligning stakeholders as it provides clear targets and timelines for the program's progress. The other options are important as well, but they focus on specific roles, external stakeholders, or communication strategies rather than the overarching alignment through milestones.