Program Management Professional (PgMP) — Question 157

You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

Answer options

Correct answer: C

Explanation

The correct answer is C, as you are assessing the completion of hotels against the planned schedule. This process focuses on tracking the timeline and ensuring that the program stays on track according to the original schedule. Options A and B are incorrect because they relate to scope and performance metrics, while D pertains to addressing issues rather than monitoring schedule adherence.