Program Management Professional (PgMP) — Question 156
You are a program manager of a program. You are required to compile performance data of your program. These data will be sent to relevant stakeholders. You are reviewing the status reports of all projects including the costs, schedule, scope, risks, and other performance data.
In which of the following processes are you working on?
Answer options
- A. Plan Communication
- B. Distribute Information
- C. Report Program Performance
- D. Monitor and Control Program Performance
Correct answer: D
Explanation
The correct answer is D, as this process involves tracking and overseeing the program's performance metrics, including costs, schedule, and risks. Options A and B relate to communication plans and information distribution, while option C focuses on reporting, which is a step that comes after monitoring and controlling performance.