Program Management Professional (PgMP) — Question 156

You are a program manager of a program. You are required to compile performance data of your program. These data will be sent to relevant stakeholders. You are reviewing the status reports of all projects including the costs, schedule, scope, risks, and other performance data.
In which of the following processes are you working on?

Answer options

Correct answer: D

Explanation

The correct answer is D, as this process involves tracking and overseeing the program's performance metrics, including costs, schedule, and risks. Options A and B relate to communication plans and information distribution, while option C focuses on reporting, which is a step that comes after monitoring and controlling performance.