Program Management Professional (PgMP) — Question 154

You are the program manager for your organization and are coaching your project managers on the program's schedule. Alice wants to know what the schedule control process creates. All of the following are outputs of the schedule control process except for which one?

Answer options

Correct answer: B

Explanation

The correct answer is B, as schedule variances are actually inputs to the schedule control process rather than outputs. The other options, such as stakeholder communication information, program schedule updates, and change requests, are indeed outputs that result from controlling the schedule.