Program Management Professional (PgMP) — Question 153

Wanda is the program manager for her organization. Her program team consists of resources from across the organization - many of whom have not worked together before. Wanda thinks that she'll need to complete some team development but would like to focus the development on the materials and activities that the program team will need to complete in the program. What plan should Wanda reference and update to complete her team development process?

Answer options

Correct answer: A

Explanation

The correct answer is A, the Training plan, because it directly addresses the skills and knowledge the team needs to effectively perform their roles in the program. The other options, such as the Communications management plan, Staffing management plan, and Requirements management plan, do not specifically focus on the training and development needs of the team.