Program Management Professional (PgMP) — Question 15

The program manager has a global program with five component projects. The program sponsor wants the management plans, processes/procedures, and technology to be uniform across the program. The requirements will create issues and result in increased costs The program sponsor is new and has imposed these new requirements six months into a three-year program.
What should the program manager do next?

Answer options

Correct answer: B, C

Explanation

The correct answer is B because it emphasizes collaboration and ensures that the program manager considers the perspectives of stakeholders and project managers before presenting a well-informed option to the sponsor. Option A is incorrect as blindly accepting demands without consulting others can lead to further complications. Option C is insufficient as it does not proactively address the sponsor's requirements, and option D, while informative, does not involve providing actionable solutions to the sponsor.