Program Management Professional (PgMP) — Question 149
Which of the following is NOT true regarding the program work breakdown structure (WBS)?
Answer options
- A. It defines a program and groups the program's discrete work elements in a way that helps organize and define the total work scope of the program.
- B. It subdivides the program deliverables to work packages that are linked to the activities within the program.
- C. It defines all the work and only the required work for the program.
- D. It subdivides the program deliverables to work packages that are linked to the activities within the program.
Correct answer: C
Explanation
The correct answer is C because the WBS defines all the work required for the program, not just the necessary tasks. Options A, B, and D accurately describe the functions of a WBS in terms of organizing, subdividing deliverables, and linking them to program activities.