Program Management Professional (PgMP) — Question 149

Which of the following is NOT true regarding the program work breakdown structure (WBS)?

Answer options

Correct answer: C

Explanation

The correct answer is C because the WBS defines all the work required for the program, not just the necessary tasks. Options A, B, and D accurately describe the functions of a WBS in terms of organizing, subdividing deliverables, and linking them to program activities.