Program Management Professional (PgMP) — Question 124

What analysis type could you use in a program to compare the positive stakeholders and their position, power, and influence over your program to the same variable components of the negative stakeholders in your program?

Answer options

Correct answer: D

Explanation

Force field analysis is the correct choice as it focuses on identifying and comparing the driving and restraining forces, which in this case are the positive and negative stakeholders. Sensitivity analysis, stakeholder analysis, and Monte Carlo simulation do not specifically address the comparative evaluation of stakeholder influence and positions in the same context.