Certified Associate in Project Management (CAPM) — Question 93

When presenting a product roadmap to an adaptive team, which form of communication is the most appropriate?

Answer options

Correct answer: C

Explanation

The correct answer is C, the Story map, as it visually represents the user journey and helps adaptive teams understand the roadmap in a way that aligns with their iterative processes. Presentation slides, requirements matrix, and project management plans are more static forms of communication that may not effectively engage a team that thrives on flexibility and adaptability.