Certified Associate in Project Management (CAPM) — Question 7
What process in Project Risk Management prioritizes project risks?
Answer options
- A. Perform Qualitative Risk Analysis
- B. Perform Quantitative Risk Analysis
- C. Plan Risk Responses
- D. Implement Risk Responses
Correct answer: A
Explanation
The correct answer, A, Perform Qualitative Risk Analysis, is the process that assesses and prioritizes risks based on their impact and likelihood. Options B, C, and D do not focus on prioritization; B deals with numerical analysis of risks, C involves developing strategies to address risks, and D is about executing those strategies.