Certified Associate in Project Management (CAPM) — Question 7

What process in Project Risk Management prioritizes project risks?

Answer options

Correct answer: A

Explanation

The correct answer, A, Perform Qualitative Risk Analysis, is the process that assesses and prioritizes risks based on their impact and likelihood. Options B, C, and D do not focus on prioritization; B deals with numerical analysis of risks, C involves developing strategies to address risks, and D is about executing those strategies.