A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations.
Which output is the project manager using?

Answer options

Correct answer: B

Explanation

The correct answer is B, Verified deliverables, as this output directly relates to ensuring that the project's outputs meet the intended quality criteria. Approved change requests (A) pertain to modifications in the project, Lessons learned (C) are insights gained from the project processes, and Work performance data (D) provides raw metrics about project performance, but does not specifically confirm deliverable quality.