Certified Associate in Project Management (CAPM) — Question 66
A project manager is addressing risks and potential concerns related to stakeholder management, and is clarifying and resolving previously identified issues. In which process is the project manager engaged?
Answer options
- A. Identify Stakeholders
- B. Plan Stakeholder Engagement
- C. Manage Stakeholder Engagement
- D. Monitor Stakeholder Engagement
Correct answer: C
Explanation
The project manager is in the 'Manage Stakeholder Engagement' process, which focuses on addressing stakeholder concerns and resolving issues. The other options, such as 'Identify Stakeholders' and 'Plan Stakeholder Engagement', are focused on initial identification and planning rather than active management of ongoing stakeholder interactions.