Certified Associate in Project Management (CAPM) — Question 61

When planning communications management, what input identifies key stakeholders?

Answer options

Correct answer: C

Explanation

The project charter is essential as it outlines the project's objectives and identifies key stakeholders involved. The other options do not specifically focus on stakeholder identification; work performance information and reports are more about project execution, while the project schedule deals with timelines.