Certified Associate in Project Management (CAPM) — Question 61
When planning communications management, what input identifies key stakeholders?
Answer options
- A. Work performance information
- B. Project schedule
- C. Project charter
- D. Work performance reports
Correct answer: C
Explanation
The project charter is essential as it outlines the project's objectives and identifies key stakeholders involved. The other options do not specifically focus on stakeholder identification; work performance information and reports are more about project execution, while the project schedule deals with timelines.