Stakeholder identification and engagement should begin during what phrase of the project?
Answer options
- A. After the project management plan is completed
- B. After the stakeholder engagement plan is completed
- C. As soon as the project charter has been approved
- D. After the communications management plan is completed
Correct answer: C
Explanation
The correct answer is C because stakeholder identification and engagement should commence as soon as the project charter is approved to ensure that all relevant parties are involved from the start. Options A, B, and D are incorrect as they suggest starting engagement after other planning documents are completed, which can lead to missed opportunities for input and support.