Certified Associate in Project Management (CAPM) — Question 485
A project manager is in the process of working with stakeholders to meet their needs and expectations, and identifying and fostering communication and involvement. Which process does this typically represent?
Answer options
- A. Monitor Stakeholder Engagement
- B. Monitor Communications
- C. Manage Communications
- D. Manage Stakeholder Engagement
Correct answer: D
Explanation
The correct answer is D, Manage Stakeholder Engagement, as it focuses on actively engaging stakeholders to meet their expectations and involve them in the project. Options A and B are more about overseeing and monitoring rather than actively managing engagement, while C refers specifically to communication management, which is a part of the broader stakeholder engagement process.