Certified Associate in Project Management (CAPM) — Question 472
Which process determines the correctness of deliverables?
Answer options
- A. Verify Deliverables
- B. Validate Deliverables
- C. Review Deliverables
- D. Analyze Deliverables
Correct answer: A
Explanation