Certified Associate in Project Management (CAPM) — Question 47
What tool or technique is used in the Collect Requirements process?
Answer options
- A. Inspection
- B. Decomposition
- C. Product analysis
- D. Prototypes
Correct answer: D
Explanation
Prototypes are effective in the Collect Requirements process as they allow stakeholders to visualize and interact with potential solutions, leading to more accurate requirement gathering. While Inspection, Decomposition, and Product analysis are valuable techniques, they do not specifically focus on engaging stakeholders in a tangible way like Prototypes do.