Certified Associate in Project Management (CAPM) — Question 457
Which are required to create the schedule management plan?
Answer options
- A. Scope baseline, work breakdown structure (WBS), estimated costs, and milestone list
- B. Resource management plan, organizational process assets, activity list, and business case
- C. Enterprise environmental factors, organizational process assets, project charter, and project management plan
- D. Activity list, project statement of work, project charter, and communications management plan
Correct answer: C
Explanation
The correct answer is C because developing a schedule management plan requires understanding the project's context, which includes enterprise environmental factors and organizational process assets. Options A, B, and D include components that are not specifically required for schedule management planning, making them incorrect.