Certified Associate in Project Management (CAPM) — Question 455

Which project documents can determine the budget?

Answer options

Correct answer: B

Explanation

The correct answer is B because the basis of estimates and cost estimates provide the necessary financial projections, while the project schedule and risk register help in understanding potential impacts on the budget. The other options include documents that may support budget discussions but do not directly determine the budget itself.