Certified Associate in Project Management (CAPM) — Question 448
What is the best tool to calculate the critical path on a project?
Answer options
- A. Critical chain method
- B. Graphical evaluation and review technique (GERT) diagram
- C. Gantt chart
- D. Project network diagram
Correct answer: D
Explanation
The Project network diagram is the most suitable tool for identifying the critical path because it visually represents the sequence of tasks and their dependencies. While the Critical chain method, GERT diagram, and Gantt chart serve other project management purposes, they do not specifically focus on calculating the critical path.