Certified Associate in Project Management (CAPM) — Question 447
A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs to make this decision?
Answer options
- A. Organizational process assets
- B. Change management plan
- C. Communications management plan
- D. Resource management plan
Correct answer: C
Explanation
The correct answer is C, the Communications management plan, as it outlines how information will be communicated to stakeholders, including the level of detail required. The other options, while important, do not specifically address the communication requirements and stakeholder engagement necessary for this report.