When should Project Risk Management be conducted?

Answer options

Correct answer: D

Explanation

Project Risk Management should be an ongoing process that occurs throughout the project lifecycle to identify, analyze, and respond to risks as they arise. Options A, B, and C suggest limited timeframes that do not encompass the continuous nature of risk management.