When should Project Risk Management be conducted?
Answer options
- A. Project Planning
- B. Monitoring and Controlling
- C. Quality Planning
- D. Throughout the project lifecycle
Correct answer: D
Explanation
Project Risk Management should be an ongoing process that occurs throughout the project lifecycle to identify, analyze, and respond to risks as they arise. Options A, B, and C suggest limited timeframes that do not encompass the continuous nature of risk management.