Project managers play a key role in performing integration on a project. What are the three different levels of integration?
Answer options
- A. Process, cognitive, and context
- B. Complexity, understand, and change
- C. Interact, insight, and leadership
- D. Communication, knowledge, and value
Correct answer: A
Explanation
The correct answer, A, identifies the three levels of integration that project managers must address: process, cognitive, and context. Options B, C, and D do not represent the recognized levels of integration within project management, making them incorrect.