Certified Associate in Project Management (CAPM) — Question 414

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

Answer options

Correct answer: A

Explanation

The correct answer, A, includes all critical components that must be documented in the risk register, such as identified risks, their potential owners, and responses. The other options contain elements that are either incomplete or not required for the risk register, making them incorrect choices.