Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
Answer options
- A. List of identified risks, potential risk owners, list of potential risk response
- B. List of identified risks, list of causes, list of risk categories
- C. Short risk titles, list of potential risk owners, list of impacts on objectives
- D. List of activities affected, list of potential risk responses, list of causes
Correct answer: A
Explanation
The correct answer, A, includes all critical components that must be documented in the risk register, such as identified risks, their potential owners, and responses. The other options contain elements that are either incomplete or not required for the risk register, making them incorrect choices.