Certified Associate in Project Management (CAPM) — Question 413

Which of the following sets are inputs to the Collect Requirements process?

Answer options

Correct answer: B

Explanation

The correct answer is B because the Collect Requirements process relies on the project charter and business documents to gather and define requirements. The other options include items that are either outputs or not directly relevant as inputs for this particular process.