Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
Answer options
- A. Risk, resource, and communications management plans
- B. Scope, quality, and resource management plans
- C. Procurement, integration, and risk management plans
- D. Communications, schedule, and cost management plans
Correct answer: A
Explanation
The correct answer is A because the stakeholder engagement plan relies specifically on the risk, resource, and communications management plans to effectively identify and engage stakeholders. The other options include plans that do not directly contribute to stakeholder engagement, making them less relevant for this specific purpose.