Certified Associate in Project Management (CAPM) — Question 407
A project manager is identifying the risks of a project. Which technique should the project manager use?
Answer options
- A. Representations of uncertainty
- B. Prompt lists
- C. Audits
- D. Risk categorization
Correct answer: B
Explanation
The correct answer is B, as prompt lists are specifically designed to help project managers identify risks by providing a structured format to consider various risk factors. Options A, C, and D do not focus on the initial identification of risks but rather on analyzing or categorizing them after they have been recognized.