Certified Associate in Project Management (CAPM) — Question 40
What is the purpose of the Manage Quality process?
Answer options
- A. To translate the quality management plan into executable quality activities.
- B. To monitor and record the results of executed quality management activities.
- C. To determine if project activities comply with organizational and project policies.
- D. To identify project deliverables and quality requirements and/or standards.
Correct answer: A
Explanation
The correct answer is A because the Manage Quality process focuses on turning the quality management plan into specific, actionable activities that can be executed. Options B, C, and D describe different aspects of quality management but do not capture the primary purpose of executing the quality management plan.