Certified Associate in Project Management (CAPM) — Question 39
What process is included in Project Integration Management?
Answer options
- A. Monitor and Control Project Work
- B. Control Scope
- C. Control Schedule
- D. Develop Team
Correct answer: A
Explanation
The correct answer is A, as 'Monitor and Control Project Work' is a key process in Project Integration Management that involves tracking, reviewing, and regulating progress and performance. The other options, while important in project management, focus on specific areas such as scope, schedule, and team development, rather than integration.