Certified Associate in Project Management (CAPM) — Question 359
The project manager is working with some functional managers and stakeholders on the resource management plan. Which elements may be included in this plan?
Answer options
- A. Team values, team agreements, and conflict resolution process
- B. Conflict resolution process, communication guidelines, and meeting schedules
- C. Team roles and responsibilities, team management, and training plan
- D. Resource requirements, resource assignments, and team performance assessments
Correct answer: C
Explanation
Option C is correct because it specifically addresses the roles, management, and training necessary for effective team functioning within the resource management plan. The other options focus on different aspects such as conflict resolution and communication, which are important but do not directly pertain to the core resource management components.