Certified Associate in Project Management (CAPM) — Question 358

A project stakeholder is requesting changes to the project plan. Which process group addresses this?

Answer options

Correct answer: D

Explanation

The correct answer is D, as the Monitoring and Controlling Process Group is responsible for tracking, reviewing, and regulating the progress and performance of the project. Options A, B, and C do not specifically address the process of managing changes; they focus on initiating, planning, and executing, respectively.