The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?
Answer options
- A. Monitor Communications
- B. Plan Communications Management
- C. Manage Communications
- D. Manage Stakeholder Engagement
Correct answer: C
Explanation
The project manager is involved in 'Manage Communications' as it focuses on the distribution of project information and retrieval of documents. 'Monitor Communications' relates to overseeing the effectiveness of communication, 'Plan Communications Management' is about strategizing how communication will occur, and 'Manage Stakeholder Engagement' focuses on interactions with stakeholders rather than communication management.