Certified Associate in Project Management (CAPM) — Question 345

Which of the following are outputs from the process of creating a work breakdown structure (WBS)?

Answer options

Correct answer: B

Explanation

The correct answer is B because the outputs of a WBS include the scope baseline, which defines the approved version of the project scope, and updates to project documents. Options A, C, and D do not include the correct outputs associated with the WBS process.