Certified Associate in Project Management (CAPM) — Question 345
Which of the following are outputs from the process of creating a work breakdown structure (WBS)?
Answer options
- A. Project scope statement and accepted deliverables
- B. Scope baseline and project documents update
- C. Accepted deliverables and enterprise environmental factors
- D. Scope baseline and work performance information
Correct answer: B
Explanation
The correct answer is B because the outputs of a WBS include the scope baseline, which defines the approved version of the project scope, and updates to project documents. Options A, C, and D do not include the correct outputs associated with the WBS process.