In an agile and adaptive project, which scope management entity involves stakeholder engagement?
Answer options
- A. Collect Requirements
- B. Create work breakdown structure (WBS)
- C. Plan Scope Management
- D. Scope Baseline
Correct answer: A
Explanation
The correct answer is A, as collecting requirements is a process that actively involves stakeholders to ensure their needs and expectations are captured. The other options, such as creating a work breakdown structure, planning scope management, and establishing a scope baseline, do not directly engage stakeholders in the same manner.