Certified Associate in Project Management (CAPM) — Question 342
Which document can help a project manager to leverage historical project information?
Answer options
- A. Lessons learned register
- B. Schedule baseline
- C. Work performance data
- D. Deliverable acceptance forms
Correct answer: A
Explanation
The Lessons learned register is specifically designed to capture and utilize insights from previous projects, making it invaluable for project managers looking to improve future project outcomes. The other options, while useful in project management, do not focus on historical information in the same way; a Schedule baseline tracks current project timelines, Work performance data reflects ongoing performance, and Deliverable acceptance forms pertain to project completion.