Certified Associate in Project Management (CAPM) — Question 329
Which are the competing constraints that a project manager should address when tailoring a project?
Answer options
- A. Cost, scope, schedule
- B. Sponsorship, risk, quality
- C. Schedule, sponsorship, scope
- D. Resources, quality, communication
Correct answer: A
Explanation
The correct answer is A, as cost, scope, and schedule are the primary constraints known as the project management triangle. While the other options mention important aspects of project management, they do not represent the fundamental competing constraints that directly impact project delivery.