Certified Associate in Project Management (CAPM) — Question 323
Which tools and techniques will a project manager use to develop a project charter?
Answer options
- A. Project manager experience, expert judgment, scope statement, and meetings
- B. Lessons learned database, interpersonal and team skills, cost baseline, and meetings
- C. Expert judgment, data gathering, scope statement, schedule baseline, and meetings
- D. Expert judgment, data gathering, interpersonal and team skills, and meetings
Correct answer: D
Explanation
The correct answer, D, includes essential skills like expert judgment and interpersonal skills that are crucial for developing a project charter. Options A, B, and C contain elements that may not directly contribute to the charter development process, such as scope statement or cost baseline, which are more relevant to later project phases.