Certified Associate in Project Management (CAPM) — Question 322

Which action should the project manager take after the team finishes executing the scope?

Answer options

Correct answer: A

Explanation

The correct answer, A, emphasizes the importance of verifying that the deliverables meet the required standards and satisfy the customer. Option B is incorrect because acceptance should only occur after verification. Option C introduces unnecessary changes before approval, which is not standard procedure. Option D focuses on change requests but overlooks the critical step of verifying deliverables.