Certified Associate in Project Management (CAPM) — Question 32
A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?
Answer options
- A. Early requirements gathering
- B. Feedback analysis
- C. Progressive elaboration
- D. Requirements documentation
Correct answer: C
Explanation
The correct answer is C, Progressive elaboration, as it involves gradually refining and detailing the project requirements based on feedback received during development. Options A and B do not emphasize the iterative aspect of refining requirements, while D refers to the process of documenting rather than evolving requirements through feedback.