Certified Associate in Project Management (CAPM) — Question 31
For what protect management process is work performance information an output?
Answer options
- A. Implement Risk Responses
- B. Plan Stakeholder Engagement
- C. Monitor Stakeholder Engagement
- D. Plan Quality Management
Correct answer: C
Explanation
The correct answer is C, as Monitor Stakeholder Engagement involves tracking stakeholder interactions and measuring their effectiveness, which generates work performance information. The other options either focus on planning or implementing responses rather than monitoring and assessing ongoing performance.