Certified Associate in Project Management (CAPM) — Question 310
Once the make-or-buy analysis is completed, which document defines the project delivery method?
Answer options
- A. Procurement statement of work (SOW)
- B. Procurement strategy
- C. Terms of reference
- D. Change request
Correct answer: B
Explanation
The Procurement strategy outlines the approach for acquiring goods and services for the project, defining the delivery method. The Procurement statement of work (SOW) provides details on the work required but does not define the delivery method. Terms of reference and Change request are not focused specifically on the procurement method.