A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?
Answer options
- A. Monitor and Control Project Work
- B. Direct and Manage Project Work
- C. Close Project or Phase
- D. Perform Integrated Change Control
Correct answer: D
Explanation
The correct answer is D, Perform Integrated Change Control, as this process specifically involves reviewing and approving changes to project documents and deliverables. The other options, while related to project management, refer to different aspects: A focuses on overseeing project performance, B pertains to executing project activities, and C is about finalizing the project or a phase.