During project execution, a key resource leaves the team for another job. What should the project manager do in this situation?
Answer options
- A. Submit a change request for additional budget to secure a project resource.
- B. Distribute work to other team members to reduce impact to the project schedule.
- C. Consult with the functional manager for a replacement resource.
- D. Consult the risk register for an appropriate risk response.
Correct answer: C
Explanation
The correct answer is C because consulting with the functional manager is essential to find a replacement resource quickly and maintain project continuity. Options A and B may be necessary later but do not address the immediate need for a replacement. Option D is not applicable as the situation does not involve a risk that was previously identified in the risk register.