Certified Associate in Project Management (CAPM) — Question 271

A business analyst is working on a project that follows an adaptive life cycle. Due to budgetary constraints, the sponsor asks the team to focus on critical requirements.

What should the business analyst do?

Answer options

Correct answer: B

Explanation

The correct answer is B, as prioritizing requirements allows the team to focus on the most critical aspects that align with budget constraints. While tracing, documenting, and validating requirements are important, they do not directly address the need to concentrate on the most vital requirements in a limited budget context.